Alternative Methods:
Traditionally, the radios that will be placed at each site are used to complete the task of optimizing the path.However, there are several reasons for not utilizing the radios to complete the process. The radios may not be available at the time the test has been scheduled or their reliability may be questionable, thus alternate methods are needed. Another possible reason the radios might not be able to be used is that the FCC permit shave not been granted, but the contractor needs to complete the path test on time to meet the customer’s requirements, or ahead of expected turbulent weather. In addition, if the anticipated path is questionable, a quick, cost effective, reliable method is needed to test the link, prior to the significant investment of constructing towers, purchasing radios and other expensive equipment and hardware, etc.